![]() |
|
|
|
The U.S. Army Corps of Engineers (COE) released approximately 10,000 cfs from Prado Dam during all or portions of seven days from January 11th, through January 17th. This is the highest release ever from Prado, with the previous maximum being 5,900 cfs. On January 20th, the COE lowered the Prado outflow to approximately 100 cfs to allow for an in-channel topographic survey over the SARI line and visual observation of erosion at manholes and pipeline crossings. The results of the visual survey indicate additional erosion has occurred around the SARI facilities. On a positive note, the two grade stabilizers installed in November – December 2004, appear to have performed as expected. However, the channel widened at these locations requiring extension of the grade stabilizer to the new channel limits. Erosion was noted at several manholes with the most significant erosion occurring around Manhole 1078 and the access road to it. It was further noted that river flow topped Manholes 1097, 1127, 1152 and 1203. However, the manhole lids are bolted and the pre-cast concrete sections strapped together with stainless steel straps. It appears these measures prevented significant manhole damage and river water inflow. As a result of the high releases, SAWPA is proposing the following actions. These actions are being coordinated with OCSD for development of the emergency repairs to be implemented immediately:
Emergency Repairs Provide additional rip-rap protection at Manholes 1078, 1089, 1097, 1132, 1152, 1165, and 1172. Restore access roads including two channel crossings as required only to complete repairs; further repairs to be completed this summer. Additional work is also required at the following manholes, but is not deemed to require emergency repair: Restore manhole access roads to each manhole; provide additional rip-rap protection around Manholes 1105, 1117, 1127, and 1203.
Maintenance
of
Access Roads and Manholes The following is a listing of the work to be performed:
OCSD directed Jamison Engineering to restart this work in late December after completion of the two grade stabilizers, but the work has been placed on hold due to the high Prado Dam releases.
Emergency Response Plan (ERP) For recent information on flows being allowed through Prado Dam, please click on this link to the COE web site. For additional information please contact Rich Haller at 951-354-4240.
|
|
|
Visitor Number:
|
|
|
Home About the Watershed About SAWPA Map to SAWPA Photo Gallery Glossary Members Commission Calendar Map Server Document Server Email FTP Site Departments Engineering Projects Planning Projects Other Projects Legislation Links News/Press Employment Contacts RFPs San Jacinto River Watershed Council Privacy Policy |
|
|
Copyright: Santa Ana Watershed
Project Authority, 2002 |
|